Liberty, Maywood projects could be first in line to be completed with bond dollars

May 18, 2012

NEW — 1:20 p.m. May 18, 2012

The Issaquah School District is wasting no time when it comes to putting its recently-approved $219 million bond dollars into action.

The school board reviewed a preliminary schedule of projects and timeline for school construction and other district upgrades at its May 9 meeting. Some projects could begin as soon as July and others extend through the end of 2019.

“Somebody has to be first, and somebody has to be last,” said Jacob Kuper, chief operations officer for the district.

Phase 2 construction of Liberty High School and Phase 2 at Maywood Middle School are first in line with finishes projected by the end of 2013. At the caboose of the tentative timeline is the reconstruction of Sunny Hills Elementary School, which wouldn’t finish until December 2018.

Construction to improve Skyline High School’s stadium would begin April 2013 and run through September 2014. As a result, Skyline’s football team is likely to play away games for the entire 2013 season. Issaquah High School will have the same problem a few years later when its stadium remodel takes place from April 2016 to August 2017.

This summer, the district hopes to install artificial turf on the athletic fields at Beaver Lake and Maywood middle schools. It would then install turf fields at Pine Lake and Pacific Cascade middle schools the following summer.

“We didn’t want to take all the fields out over the course of the summer because it would be a huge impact on the community,” said Steve Crawford, director of capital projects for the district.